TURBINE INSTALLED COST ($/KW) — CCGT $950 2019 $970 2021 $1,280 2023 $2,000 2025★ $0 +110% in 6 YEARS (2019→2025) IMPACT ON 1,440 MW LNG POWER ISLAND 2019 PRICING $1.37B @ $950/kW 2025 PRICING $2.88B @ $2,000/kW → +$1.51B Per 1,440 MW power island (e.g. Plaquemines) THREE MANUFACTURERS CONTROL 90% OF SUPPLY GE Vernova · Siemens Energy · Mitsubishi Heavy Industries
2.1×turbine cost increase 2019 → 2025
$2,000/kW today vs $950/kW in 2019
7–8 yrdelivery lead time today
100 GWGE Vernova backlog Q1 2026

When LNG project developers in Houston and Calgary model a new liquefaction terminal, they use cost assumptions built from comparable projects. For gas turbines — the machine that drives liquefaction compression or generates the power to do it — those assumptions are built on 2019 and 2020 data. In 2025, combined-cycle gas turbine power plants cost $2,000 per kilowatt of installed capacity. In 2019, they cost $950. The equipment on which North American LNG projects depend has more than doubled in price. Almost nobody's FID model reflects that.

01 — The Cost Shock$950 to $2,000 per Kilowatt — In Six Years

Gas turbine and gas plant cost data is not opaque. The EIA publishes it annually. Gas Turbine World publishes detailed per-kW benchmarks. GridLab and the American Public Power Association both produced reports in September 2025 documenting the escalation. The data is available. What is missing is the systematic application of this data to LNG project economics — where turbine costs have historically been treated as a known, stable line item rather than a variable that has compounded at 12–15% per year for five consecutive years.

Gas Turbine Installed Cost (Combined Cycle, USD/kW) — 2019 to 2025
Publicly confirmed data from EIA, GridLab, Gas Turbine World · The price curve LNG project models have not updated
$0 $400 $800 $1,200 $1,600 $2,000 $950/kW $950/kW $1,270/kW $1,600/kW $2,000/kW ★ 2019 2021 2023 2024 2025★ (EIA confirmed) (projects for 2026-27) (recent projects confirmed) USD / kW installed
Sources: EIA Annual Electric Generator Data (2021: $948/kW CCGT, confirmed); GridLab / Energy Futures Group / Halcyon report (September 2025: recent projects at $2,000/kW confirmed); American Public Power Association (September 2025); Gas Turbine World 2024 Handbook ($950/kW for H-class combined cycle). 2024 figure directional interpolation. Star (★) denotes publicly confirmed figure from GridLab September 2025 report. Combined cycle (CCGT) plant costs — including gas turbine, HRSG, steam turbine, balance of plant, and EPC. Equipment-only gas turbine costs (OEM pricing) have risen 2–3× per market practitioner intelligence.

The relevant comparison for an LNG project developer is not the cost of electricity from a gas turbine — it is the cost of the gas turbine capital equipment needed to run the project. A 1,440 MW power island (the configuration used at Plaquemines LNG for its electric-drive liquefaction trains) cost approximately $1.37 billion at 2019 pricing. At today's confirmed cost of $2,000/kW, the same 1,440 MW power island costs $2.88 billion. The difference — $1.51 billion — is sitting invisibly in the capex exposure of every unbuilt LNG project that modelled turbine costs before 2022.

The Insight LNG Finance Teams Are Missing
+$1.5B

The turbine price escalation since 2019 has added approximately $1–3 billion of unmodelled capex to every large North American LNG project that has not yet locked in turbine pricing at a fixed contract. Projects that FID'd before 2022 — Sabine Pass, early Corpus Christi trains, LNG Canada Phase 1 — locked in turbine costs at 2015–2019 pricing. Every project FID'ing in 2024–2026 pays 2025 prices. That cost differential is not a rounding error. It is a first-mover advantage worth hundreds of millions of dollars per project — and it does not appear in any public LNG project cost comparison.

02 — Three ManufacturersThe Oligopoly and the Turnaround Nobody Predicted

The three companies that manufacture heavy-duty gas turbines — GE Vernova, Siemens Energy, and Mitsubishi Heavy Industries — were in varying degrees of financial distress between 2018 and 2023. GE Power took a $23 billion write-down in 2018. Siemens Energy posted a net loss of €4.588 billion in FY2023, required state-backed guarantees to survive, and watched its shares collapse by more than 70%. Mitsubishi Power had significant delivery problems on US projects in 2019–2021. Market analysts wrote extensive notes about the structural decline of the industrial gas turbine sector. Then the energy transition, AI infrastructure, and LNG expansion all arrived simultaneously — and every assumption about that decline was inverted.

↑
GE Vernova
Cambridge, MA · NYSE: GEV
❌ GE Power: $23B write-down 2018. Catastrophic losses. GE's worst division for a decade. Analysts called gas turbines a "stranded asset."

✓ Q1 2026: Backlog + slot reservations = 100 GW, targeting 110 GW YE 2026. Total backlog: ~$150B. Data centre electrification orders: $2.4B in Q1 2026 alone — more than all of 2025 combined.
↑
Siemens Energy
Munich · XETRA: ENR
❌ FY2023: Net loss €4.6B. Siemens Gamesa wind turbine failures. State-backed guarantees needed. Shares down 70%+. Crisis year.

✓ FY2025: Profit before special items €2.36B. Free cash flow €4.66B (+2× YoY). Gas Services record profit ~€1.6B. 194 turbines sold. Order backlog: €138B (record). Shares up 300%+ in 2024.
↑
Mitsubishi Heavy
Tokyo · TYO: 7011 · via Mitsubishi Power
❌ Mitsubishi Power: Delivery problems on US projects 2019–2021. H-class ramp-up costly. Significant losses in energy systems segment.

✓ 35% of global gas turbine market share by MW (2023). Energy Systems segment growing. Fully benefiting from supply constraint. Expanding manufacturing capacity.

What caused the turnaround was not a single event but the collision of three demand pools on a supply base that had been deliberately contracted for a decade. Production capacity was cut, engineering teams were reduced, and supply chains were streamlined in response to the depressed demand of 2012–2022. Rebuilding that capacity now requires 3–5 years at minimum — regardless of how much capital the three manufacturers commit. Gas turbines and their lifecycle services are now structurally more expensive, not temporarily inflated. The margin expansion has been enabled by higher equipment prices, tighter contractual frameworks, and longer lead times — mechanisms that permanently transfer cost and risk downstream to project developers.

03 — Three Demand PoolsData Centres, LNG, and Energy Transition — All Competing Now

AI / Data Centres
$2.4B

GE Vernova booked $2.4 billion in data centre electrification orders in Q1 2026 — more than all of 2025 combined. A single large AI training campus can require 400–800 MW of firm, uninterruptible power. Microsoft, Google, Amazon, and Meta are committing to multi-gigawatt gas-backed data centre infrastructure across North America and Europe. This demand arrived suddenly and is growing every quarter.

LNG Projects
7–8 yr

Every LNG liquefaction project — mechanical drive or electric drive — is a gas turbine customer. US Gulf Coast terminals currently exporting or in construction represent well over 10,000 MW of installed turbine capacity. The next generation of projects under development across North America requires another 5,000–8,000 MW. IEEFA (October 2025) reports manufacturers advising LNG-to-power developers in Asia to plan 7–8 years ahead for turbine procurement.

Energy Transition
30–40%

Once renewable penetration exceeds 30–40% of grid capacity, dispatchable gas peaking capacity becomes a grid stability requirement — not an option. The energy transition does not replace gas turbines. At the current pace of solar and wind addition, it requires more gas peaking turbines simultaneously to backstop the variability. Europe, North America, and Asia are all in this dynamic simultaneously, competing for the same orderbook.

04 — North American LNGThe Turbine Count Nobody Has Published

Every North American LNG project is a turbine customer. The table below — built from public project filings, FERC approvals, and EIA capacity data — maps the turbine requirements and implied cost impact across the North American LNG project pipeline. The split between early movers (who locked in pre-escalation pricing) and late movers (who face today's market) is the commercial asymmetry at the heart of the article.

ProjectCapacity (MTPA)Power/Drive ConfigTurbine Pricing EraEst. Turbine Capex Impact
Sabine Pass (Cheniere)
Cameron Parish, LA
27 MTPA (6 trains) 12 × GE LM2500+G4 aeroderivative per 2 trains (34 MW each, mech. drive) 2012–2015 pricing ✓ Locked in. Massive first-mover advantage vs today.
Corpus Christi (Cheniere)
Stages 1–3
~25 MTPA total Siemens SGT-800 aeroderivative mech. drive; Stage 3: Baker Hughes LM9000 Stage 1–2: 2015–2017 ✓
Stage 3: 2022 pricing
Stage 3 partially exposed to escalation. Still below peak pricing.
Plaquemines LNG (Venture Global)
Phase 1 + Phase 2
~26 MTPA (36 trains) 2 × 720 MW CCGT electric drive (Baker Hughes / MHPS turbines) per phase. "5 on 2" gas + steam turbine config. FID 2022 — partially exposed 1,440 MW power island × 2 phases. Phase 1 EPC likely pre-escalation peak. Phase 2 fully exposed.
Golden Pass LNG (QatarEnergy/ExxonMobil)
Sabine Pass, TX
15.6 MTPA (3 trains) 3 trains × ~5.2 MTPA. First cargo April 2026. EPC by Zachry/CB&I/Chiyoda. FID 2019 — mid-escalation Construction delays (Zachry bankruptcy) absorbed some cost overrun. Turbines likely ordered before 2022 peak.
Port Arthur LNG Ph1 (Sempra/KKR)
Jefferson County, TX
13.5 MTPA Baker Hughes LM9000 aeroderivative mech. drive (2 per train, 70 MW each) FID June 2023 — near-peak pricing Capex: ~$13B. Turbine orders likely placed at escalated pricing. LM9000 premium unit.
Corpus Christi Stage 3 (Cheniere)
Expansion trains
10.5 MTPA Baker Hughes LM9000 × 2 per train (70 MW each) FID June 2022 — escalating market Exposure: moderate to high. Turbine costs rising through procurement window.
Rio Grande LNG Ph1 (NextDecade)
Brownsville, TX
17.6 MTPA Baker Hughes turbines (LM9000 class aeroderivative, mech. drive) FID July 2023 — peak pricing Full 2023 pricing exposure. ~$18.4B total capex. Turbine procurement at highest cost era.
LNG Canada Phase 2 (Shell-led)
Kitimat, BC
14 MTPA Gas turbines for compression; plans to electrify "when BC Hydro available" (2032+). Gas turbine fallback confirmed. FID expected late 2026 — full peak pricing Phase 2 turbine procurement at 2026 market prices. $1–2B additional capex vs Phase 1 turbine assumptions.
Cedar LNG (Haisla/Pembina)
Kitimat, BC
3.3–3.75 MTPA Hydro-electric drive (BC Hydro, 214 MW). No gas turbine required for primary drive. No turbine capex exposure ✓ Hydro-electric design eliminates the turbine price shock. Direct competitive advantage vs gas-turbine-dependent projects.
CP2 LNG / Commonwealth LNG
Louisiana, pending FID
28 MTPA combined Turbine requirements TBD — pending FID Post-2025 — maximum pricing exposure Full 2026+ turbine pricing if FID proceeds. Could represent $2–4B turbine capex exposure vs comparable pre-2022 project assumptions.
The First Mover Advantage — Quantifying the Gap

The divergence between early-mover LNG projects (Sabine Pass, Corpus Christi Stages 1–2) and late-mover projects (Port Arthur, Rio Grande, CP2) is material and permanent. A project that locked in 12 LM2500+G4 turbines at 2012 pricing locked in approximately $400–500M of compression equipment. The same configuration at 2025 aeroderivative turbine pricing costs $900M–1.2B. The difference — $400–700M per project — represents a structural delivered-cost advantage for early movers that compounds across the project's 20-year operating life through lower capital recovery costs.

Cedar LNG takes this advantage further: by using BC Hydro electric drive (214 MW), it eliminates gas turbine capex exposure entirely. In a world where the turbine itself has become the most expensive and hardest-to-source piece of equipment in the project, designing around it is a commercial decision that looks increasingly prescient.

05 — The GE Vernova Backlog100 Gigawatts and Growing

GE Vernova Gas Power Backlog + Slot Reservations (GW) — Quarterly 2025–2026
Confirmed from GE Vernova SEC filings each quarter · Growing 120% in 12 months
0 20 40 60 80 100 50 GW 55 GW 62 GW 83 GW 100 GW ★ Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026★ → 110 GW target YE 2026 Gigawatts (GW)
Source: GE Vernova SEC filings — Q1 2025 (April 23, 2025 press release: 29 GW backlog + 21 GW slot reservations = 50 GW); Q2 2025 (July 2025: 55 GW); Q3 2025 (October 22, 2025: 62 GW); Q4 2025 (January 2026: 83 GW); Q1 2026 (April 2026: 100 GW). Includes firm equipment orders and slot reservation agreements not yet converted to binding orders. YE 2026 target of 110 GW per GE Vernova Q1 2026 management guidance. Star (★) = most recent confirmed quarter.

06 — The Commercial TermsWhat Buyers Face Today vs Three Years Ago

The commercial terms for large gas turbine procurement have been rewritten by the supply-demand imbalance. Three years ago, manufacturers competed for orders. Today, buyers compete for slots.

Term2019–2021 (Buyer's Market)2025–2026 (Seller's Market)
Equipment price $900–950/kW (CCGT installed). Discounts common. Sellers competing on price. $2,000/kW (CCGT installed). No discounts. List price or walk away. Equipment-only 2–3× on OEM pricing per market intelligence.
Upfront payment Milestone-based, back-loaded. Small advance payments at contract signing. ~20% non-refundable at order. One developer paid $25M to reserve a single delivery slot (IEEFA, October 2025).
Delivery timeline 2–3 years typical for large-frame turbine from order to delivery. Post-2030 for new orders in most cases. 7–8 years advised by manufacturers. Delivery slots sold into next decade.
Contract terms Buyer-favourable. Competitive bids. Price protection, cancellation flexibility. Seller-dictated. Non-cancellable orders. Inflation pass-through clauses. OEM-preferred service terms mandatory.
Service contracts Competitive market, third-party service providers viable alternative. 15–20 year OEM service agreements increasingly mandatory at purchase. Service pricing reflects OEM pricing power — lifecycle cost increase exceeds equipment price increase.

07 — Global ImpactSoutheast Asia's LNG-to-Power Problem

The turbine shortage has a particularly acute dimension for Southeast Asian energy markets, where multiple governments have committed to coal-to-gas switching programs and new LNG import infrastructure between 2025 and 2030. Vietnam, the Philippines, Bangladesh, and Pakistan each have LNG-to-power projects targeting commissioning between 2027 and 2030. With 7–8 year turbine lead times, these projects needed to place turbine orders between 2019 and 2023 to receive delivery on time.

IEEFA documented in October 2025 that manufacturers are explicitly advising LNG-to-power project developers in Southeast Asia to plan 7–8 years ahead for turbine procurement — a timeline that is longer than most of these countries' LNG project development cycles. Projects that have not yet ordered turbines cannot receive them in time for their stated commissioning dates. The LNG supply that North American exporters are contracting to these markets depends on receiving terminals and gas-fired power plants that, on current turbine procurement timelines, cannot be built to schedule.

This creates a specific commercial exposure for North American LNG exporters: long-term offtake agreements with Southeast Asian buyers are, in some cases, contingent on infrastructure build-out that is gated by turbine availability the buyers have not yet secured. Understanding which buyers have placed turbine orders and which have not is due diligence that LNG commercial teams need to incorporate into counterparty analysis.

08 — What Comes NextFive Years of Constraint, Then a Different Market

The production capacity expansion is real and happening. GE Vernova has committed capital to its Schenectady facility. Siemens Energy is expanding manufacturing in Europe and the Middle East. Mitsubishi Power is investing in its US and Japanese facilities. These expansions will begin to provide relief — but not before 2030. The lead time from manufacturing capital investment to first turbine delivery from expanded capacity is 3–5 years.

Beyond the 2030 horizon, several factors could accelerate rebalancing: long-duration battery storage at scale reduces the peaking gas turbine requirement; small modular reactors provide an alternative to gas-fired baseload; hydrogen-capable turbines may serve some demand categories. But none of these alternatives are meaningful at scale before 2030–2032. For the next five years, the three manufacturers will control the pace at which the world can build the power infrastructure it has committed to building.

For North American LNG practitioners — commercial teams, project developers, investors — the practical implication is direct: turbine procurement must be initiated at project development, not at FID. Projects that integrate turbine procurement strategy into their pre-FID planning will have significantly better economics, more reliable schedules, and stronger offtake counterparty positions than projects that treat turbines as a standard EPC procurement item. The companies that understood this in 2020 and 2021 already have their turbines. The ones that are learning it now are competing for post-2030 delivery slots at 2025 prices.